Receiving Party Delivery Points List | |||||
---|---|---|---|---|---|
Delivery Point | Max. Reserved FT1 Capacity | Code | |||
Sierra Pacific Power Co. | 105,744 | SPPC1 | |||
Southwest Gas - Nevada | 94,977 | SWGN1 | |||
Southwest Gas - California | 11,148 | SWGC1 | |||
Avista Corporation | 17,908 | WPNG1 |
Master Receipt Point List | |||||
---|---|---|---|---|---|
Receipt Point | Max. Daily Quantity | Code | |||
Idaho/Nevada Interconnect | 157,848 Dth | NWPL1 | |||
LNG Plant | 71,959 Dth * | LNGP1 | |||
* Paiute's LNG Plant was designed as a peaking facility to be used during the Winter period (November 1 to March 31). |
FT-1 Daily Reserved Mainline Capacity | |||||
---|---|---|---|---|---|
January | February | March | April | May | June |
229,807 | 229,807 | 229,807 | 138,780 | 138,780 | 138,780 |
July | August | September | October | November | December |
138,780 | 138,780 | 138,780 | 138,780 | 229,807 | 229,807 |